search
Barnsley
Batley
Bedale
Beverley
Bingley
Bradford
Bridlington
Brighouse
Castleford
Catterick Garrison
Cleckheaton
Cottingham
Darlington
Dewsbury
Doncaster
Driffield
Elland
Filey
Goole
Guisborough
Halifax
Harrogate
Hawes
Hebden Bridge
Heckmondwike
Hessle
Holmfirth
Huddersfield
Hull
Ilkley
Keighley
Knaresborough
Knottingley
Leeds
Leyburn
Liversedge
Malton
Mexborough
Middlesborough
Mirfield
Morley
Normanton
Northallerton
Ossett
Otley
Pickering
Pontetfract
Pudsey
Redcar
Richmond
Ripon
Rotherham
Saltburn-by-the-Sea
Scarborough
Selby
Settle
Sheffield
Shipley
Skipton
Sowerby Bridge
Stockton-on-Tees
Tadcaster
Thirsk
Todmorden
Wakefield
Wetherby
Whitby
Yarm
York
Planned Roadworks In Yorkshire And The Humber: Monday 26 March to Sunday 1 April 2018
The following summary of planned new and ongoing road improvements over the coming week is correct as of Friday 23 March and could be subject to change due to weather conditions or unforeseen circumstances. All our improvement work is carried out with the aim of causing as little disruption as possible.

M1 junction 33 Catcliffe

The northbound entry slip road will be fully closed overnight on Monday 26 March for technology work. The closure will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes.

M1 junction 40 to junction 41 Carr Gate

The northbound entry slip road at junction 41 will be fully closed overnight on Monday 26 March and the northbound entry slip road at junction 40 will be fully closed overnight for two nights from Tuesday 27 March. The southbound entry slip road at junction 44 will be fully closed overnight on Tuesday 27 March. The closures for technology work will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes.

M62 junction 34 to junction 35 Langham

The eastbound carriageway will be fully closed overnight for three nights from Monday 26 March for bridge work. The closure will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes.

M62 junction 32 Castleford to junction 30 Rothwell

The westbound carriageway will be fully closed overnight for three nights from Monday 26 March from junction 31 to junction 30 for resurfacing work. The closure will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes.

M621 junction 1 Beeston to junction 7 Stourton

The anticlockwise carriageway will be fully closed overnight for three nights from Monday 26 March. The clockwise and anticlockwise will be in narrow lanes with a 30mph speed restriction until June for the installation of concrete barrier. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes. Updates on the scheme are available on twitter #m621.

M180 junction 4 Broughton

The eastbound carriageway will be fully closed between the slip roads for technology work on Monday 26 March. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes.

A1T Barnsdale to Ferrybridge

The southbound carriageway will be fully closed overnight for two nights from Tuesday 27 March for barrier renewal work. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes. The northbound and southbound carriageway will be in narrow lanes with a 40mph speed restriction until April.

A180 Stallingbrough to Great Coates

The eastbound carriageway will be fully closed overnight on Monday 26 March. The westbound carriageway will be fully closed overnight on Tuesday 27 March. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes.

The eastbound and westbound carriageway will have a 24/7 lane 2 closure with a 50mph speed restriction until the end of March for the installation of concrete barrier.

A64 Scotchman Lane to Whitwell Duals

There will be convoy working on the eastbound carriageway for three nights from Monday 26 March (excluding weekends) for drainage work. The work will take place between 8pm and 6am.

A64 Bramham to Askham Bryan

The eastbound and westbound carriageway has a 40mph speed restriction in place until May for barrier renewal work. The speed restriction is in place 24/7.

A64 Hopgrove to Grimston

The westbound carriageway will be fully closed overnight for three nights from Monday 26 March for barrier work. The closures will take place between 8pm and 6am, and drivers will be able to follow clearly signed diversion routes.

A628 Tintwistle

There will be convoy working on the eastbound carriageway for three nights from Monday 26 March for carriageway repair work. The work will take place between 8pm and 6am.

A628

The A628 will be closed in both directions between Flouch roundabout and the Gunn Inn on Saturday 24 and Sunday 25 March between 5am and 10am to remove a tree that is overhanging the carriageway.