search
Barnsley
Batley
Bedale
Beverley
Bingley
Bradford
Bridlington
Brighouse
Castleford
Catterick Garrison
Cleckheaton
Cottingham
Darlington
Dewsbury
Doncaster
Driffield
Elland
Filey
Goole
Guisborough
Halifax
Harrogate
Hawes
Hebden Bridge
Heckmondwike
Hessle
Holmfirth
Huddersfield
Hull
Ilkley
Keighley
Knaresborough
Knottingley
Leeds
Leyburn
Liversedge
Malton
Mexborough
Middlesborough
Mirfield
Morley
Normanton
Northallerton
Ossett
Otley
Pickering
Pontetfract
Pudsey
Redcar
Richmond
Ripon
Rotherham
Saltburn-by-the-Sea
Scarborough
Selby
Settle
Sheffield
Shipley
Skipton
Sowerby Bridge
Stockton-on-Tees
Tadcaster
Thirsk
Todmorden
Wakefield
Wetherby
Whitby
Yarm
York
Tunnel Safety Concerns Reported To HSE
AMCO-Giffen vehicles at the north end of Queensbury Tunnel on 12th October. Credit: Four by Three
The Health & Safety Executive (HSE) has been asked to investigate plans for work in a disused railway tunnel which would involve the appointed contractor undertaking activities in an area designated as too hazardous to enter.

Queensbury Tunnel in West Yorkshire is currently the focus of a campaign to reopen it as part of a cycle network linking Bradford and Keighley to Halifax, but Highways England, which looks after the Victorian structure on the Department for Transport’s behalf, intends to partly infill and permanently close it at a cost to the taxpayer of £3.6 million.

The southern end of the tunnel is currently flooded to a depth of 13 feet (4 metres) following the switching-off of a pumping station which had been installed by Highways England in 2016. The lease for land on which most of the equipment is sited was forfeited last December due to the £50 annual rent not being paid for two years.

Flooding at the south end of the tunnel in September 2018, caused by Highways England's failure to pay the £50 annual rent for their pumping station. Credit: Four by Three
Following discussions between Highways England and its contractor AMCO-Giffen, plans have been developed for a new dewatering system which would involve the floodwater being pumped 1.4 miles to the north end of the tunnel. However, to implement it, heavy machinery would have to be used to create an access route through a section of the tunnel which is blocked in two places by tonnes of fallen rock and buckled scaffold platforms.

Partial collapses occurred in 2013 and 2014, resulting in an exclusion zone being established which inspectors and contractors are not allowed to enter. Its length was subsequently extended to cover 300 metres of the tunnel based on concerns that adjacent sections of its lining might also fail. The exclusion zone is identified in AMCO-Giffen’s works contract.

The HSE was notified because Highways England has not yet entered into meaningful negotiations with the landowner for a new agreement allowing its original pumping station to be turned back on.

One of two partial collapses which prevent access through the tunnel to the south of its midpoint. Credit: Forgotten Relics
Graeme Bickerdike, Engineering Co-ordinator for the Queensbury Tunnel Society, said:

“Basic health and safety principles set out a hierarchy of controls. The preferred approach is for the risks to be eliminated - in other words, instead of undertaking the work, could something else be done? Clearly, until the option of restarting the existing pumps has been absolutely ruled out, there is no justification for any physical works to be undertaken.

“The situation is entirely of Highways England’s own making so it’s incumbent upon those responsible for it to overcome their embarrassment, engage with the landowner and find a way forward that does not involve exposing the contractor’s workforce to wholly unnecessary risks. We have alerted the HSE to what’s being discussed and suggested that proactive action is needed.”






The HSE has also been asked to consider whether the flooding should have been resolved before preparatory works got underway in the tunnel on 1st October, resulting in personnel currently having only one viable means of escape. If a collapse occurred between their site of work and the exit - a possibility recognised in the contractor’s construction plan - their only options would be to swim 400 metres through the floodwater or, if the route was not completely blocked, take the risk of passing through the failed section of tunnel.

Tunnel Safety Concerns Reported To HSE, 23rd October 2018, 15:56 PM